It is important for contractors to understand when a lessor’s interest may become lienable. In the event that a contractor performs work at the insistence of a lessee, and the lessee is unable to pay for that work, the only other recourse for actually collecting money may be going after the lessor. If the lessor’s interest is not lienable, the contractor may not be able to collect his money under the contract with the lessee. Thus, it is important to be cognizant of the situations you, as a contractor, enter into so as to maintain the highest probability of being paid.
Under Utah Code section 38-1-3, a lessee may be an “owner” within the meaning of the statute and his leasehold may be subject to a mechanic’s lien. Utah Code Ann. § 38-1-3 (Lexis 2005); see also
Interiors Contracting Inc. v. Navalco, 648 P.2d 1382 (Utah 1982). Mechanic’s liens, however, can only attach to the extent of the interest of the consenting “owner” of the realty. The question is whether the improvements made for the tenant are made at the insistence, implied or expressed, of the fee owner or any person acting as its agent or contractor or otherwise having the fee owner’s authority. Thus, in
Buehner Block Company v. Glezos, 6 Utah 2d 226, 310 P.2d 517 (1957), where a lessee operated a restaurant on the leased premises and the lessee caused an addition to be added onto the building, the court held that the materialmen’s liens were only enforceable against the lessee’s interest and not against the lessor’s interest because the work had not been performed at his insistence although the lessor had given his approval to the lessee for the addition. See also
Interiors Contracting, Inc. v. Navalco 648 P.2d 1382 (Utah 1982).
Utah courts have held similarly in other cases. In
Martindale v. Adams, 777 P.2d 514 (Utah Ct. App. 1989), the court of appeals ruled that a lessor’s interest was not lienable unless there was an implied or expressed contract between the lessor and the contractor for the work. In this case, the lessee contracted for the improvements to the property, and represented to the contractor that he owned the home. This was not the case, and the court ruled that the lessor could not be held responsible for the improvement costs.
In another case, the Utah Supreme Court ruled that there would be two instances where a lessor’s interest would be lienable for improvements sought by the lessee.
Allen Steel Co. v. Crossroads Plaza Assoc., 119 Utah Adv. Rep. 6 (Utah 1989), withdrawn by stipulation of the parties, 1991 Utah Lexis 30. First, in support of the Martindale court’s opinion, if there is an agreement, either express or implied, between the claimant and the lessor, the lessor’s interest may be lienable. Second, if the agreement between the lessor and lessee require that the lessee construct improvements to the property which substantially enhance the value of the landowner’s interest, the court held that the mechanic’s lien could attach to the landowner’s interest. Id. Because the opinion of the court was withdrawn, it carries no precedential value, but it does give contractors and lessors an idea of how the Utah Supreme Court may view a case involving a lessor’s rights and a mechanic’s lien.
The insistence of a lessor for improvements contracted for by a lessee will not necessarily be inferred from the lessor’s knowledge of the improvements where the lessor’s participation is limited to the extent the law requires an owner of property to make certain governmental applications for the improvements. In
Zions First National Bank v. Carlson, 23 Utah 2d 395, 464 P.2d 386 (1970), the court inferred that a lessor is subject to a lien for improvements by tenant if the lessor “required or obligated the lessee to construct any improvements which would substantially enhance the value” of the owner’s interest. Id. at 23 Utah 2d 401, 464 P.2d 386, 390. The Zions court further stated that:
in order to make such covenant, constitute an agency between the lessor and lessee, we are necessarily bound to look at the facts to determine whether there was an agency or not. If, on account of the shortness of the lease, the extent, costs, and character of the improvements, or other facts in evidence, such as the participation by the lessor in the erection or construction thereof, it can be seen that the improvement is really for the benefit of the lessor, and that he is having the work done through his lessee, that it can be said with justice that the lessee in such case is acting for the lessor . . .
In determining whether an agency should be implied the courts have often, perhaps of necessity, gone beyond the agreement and into the whole circumstances of the letting in order to find the answer . . . [W]here the premises are let for a specific purpose and where the nature of the premises is such that the purpose cannot be accomplished except by the making of substantial improvements to the freehold, then the tenant is, by implication, required to make such improvements. He has no other option, and hence he is the landlord’s [implied] agent to the extent of subjecting the property to a lien, this upon the theory that the landlord contemplated the necessity and required that such necessity be met.
Id. at 23 Utah 2d 400, 464 P.2d 390 (quoting Utley v. Wear, 333 S.W.2d 787, 792-793 (Mo. Ct. App. 1960)); see also
Interiors Contracting Inc. v. Navalco, 648 P.2d 1382 (Utah 1982).
It is important to note that there is an older conflicting case where a tenant was, by his written contract of lease, obligated to make improvements upon the property. The court held that this did not make him the owner’s agent in requesting the materials furnished. See
Morrow v. Merritt, 52 P. 667 (Utah 1898).